2/21 |
Mock-up of stair design in place
remains in place for 2 Sundays, Committee members to take input |
|
2/24 |
Project all-in budget to
be used for campaign purposes |
|
3/1 |
Renderings of interior and exterior
spaces complete |
|
3/4 |
Approval to move forward with design
to construction drawings for estimating purposes. Delay in this
date will result in delays in having final estimates for May
Annual Meeting |
|
3/16 |
Canvass Brochure Complete |
|
3/17 5/18 |
Ongoing Communications Efforts |
|
3/16 |
Lead Canvasser Training |
|
3/17 4/5 |
Lead Gifts Campaign |
|
4/1 |
Construction Drawings complete, estimating
begun |
|
4/5 |
Kickoff Event |
|
4/7 5/3 |
General Campaign |
|
5/1 |
Project Budget finalized based on Construction
Drawings |
|
5/3 5/18 |
Follow-up |
|
5/29 |
FRS Annual Meeting Vote whether
to commit pledged funds |
|
6/1 |
Construction Project Commences |